Westfork Municipal is using a hybrid model for a park renovation. The baselined landscaping workstream shows an S-curve where EV has diverged below both PV and AC.

What should the project manager do first?

  1. Request additional funding from the Westfork municipal council.
  2. Perform a variance analysis to identify the cause of the deviations.
  3. Transition the workstream to a Scrum framework to increase velocity.
  4. Crash the landscaping schedule by adding more labor.