easy · Project Management Professional hybrid

Kestrel Civic is developing a hybrid traffic-monitoring system. The sensor hardware is managed via a predictive baseline, while the analytics dashboard is developed in sprints. During a RACI mapping session for the activity "Approve Hardware Specifications," both the Lead Engineer and the Safety Officer want to be 'Accountable.'

What should the project manager do?

  1. Assign the Lead Engineer as Accountable and the Safety Officer as Consulted.
  2. Escalate the conflict to the Kestrel Civic steering committee for a final decision.
  3. Assign both as Accountable to reflect the shared safety and technical responsibility.
  4. Assign the Project Manager as Accountable to remain neutral.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials