easy · Project Management Professional Hybrid Approaches

Kestrel Civic is developing a hybrid traffic-monitoring system. The sensor hardware is managed via a predictive baseline, while the analytics dashboard is developed in sprints. During a RACI mapping session for the activity "Approve Hardware Specifications," both the Lead Engineer and the Safety Officer want to be 'Accountable.'

What should the project manager do?

  1. Assign the Lead Engineer as Accountable and the Safety Officer as Consulted.
  2. Escalate the conflict to the Kestrel Civic steering committee for a final decision.
  3. Assign both as Accountable to reflect the shared safety and technical responsibility.
  4. Assign the Project Manager as Accountable to remain neutral.