easy · Project Management Professional Hybrid Approaches

Westfork Municipal's hybrid project has a task: "Finalize Paving Materials Selection." In the RACI matrix, the City Architect is 'Accountable' and the Vendor is 'Responsible.'

What does 'Consulted' mean for the local Community Group in this context?

  1. They provide two-way input before a decision is made.
  2. They must approve the final selection along with the Architect.
  3. They perform the work of researching the materials.
  4. They are simply told what materials were chosen after the fact.

Sign up free to see the explanation and track your rank →