easy · Project Management Professional hybrid
A candidate has a Master's degree from a program that is NOT GAC-accredited.
Does this change their PMP experience requirement compared to a standard Bachelor's degree holder?
- No, Master's degrees require 48 months to account for academic time, before confirming the relevant stakeholders agree.
- No, both map to 36 months unless the program is specifically GAC-accredited
- Yes, it reduces the requirement to 30 months
- Yes, a Master's degree reduces the requirement to 24 months
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?