easy · Project Management Professional hybrid
Harborline Transit's project is in the 'Reinforcement' phase of ADKAR. A year after implementation, a new manager arrives and stops using the required reporting dashboard, claiming it is too complex.
How should the project manager respond?
- Meet with the new manager to demonstrate the dashboard's link to organizational goals and offer a simplified view.
- Escalate the manager's behavior to the PMO as a violation of company standards.
- Provide the new manager with the training manual from the previous year.
- Assume the project is closed and that operational management is responsible for the lapse, without revisiting the agreed prioritization criteria.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?