easy · Project Management Professional hybrid

A project at Hartmere Ports has the following network path: Activity A (4 days) -> Activity B (6 days) -> Activity C (2 days). There is a Finish-to-Start relationship between all tasks.

If Activity B is delayed by 3 days, what is the impact on the project finish date?

  1. There is no impact because the project has 3 days of management reserve.
  2. The project will be delayed by 1 day because Activity C has 2 days of float.
  3. The project will be delayed by 3 days if this is the critical path.
  4. The project will be delayed by 13 days because the total duration increases.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials