easy · Project Management Professional hybrid
A project at Hartmere Ports has the following network path: Activity A (4 days) -> Activity B (6 days) -> Activity C (2 days). There is a Finish-to-Start relationship between all tasks.
If Activity B is delayed by 3 days, what is the impact on the project finish date?
- There is no impact because the project has 3 days of management reserve.
- The project will be delayed by 1 day because Activity C has 2 days of float.
- The project will be delayed by 3 days if this is the critical path.
- The project will be delayed by 13 days because the total duration increases.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?