hard · Project Management Professional hybrid
Peakstone Rail is developing a new signaling system. The network diagram shows four paths: Path 1 is 14 weeks, Path 2 is 18 weeks, Path 3 is 21 weeks, and Path 4 is 19 weeks.
If an activity on Path 3 is delayed by 2 weeks, what is the effect on the project's completion date?
- The completion date will shift by 4 weeks due to the merge bias at the end of the project.
- Path 2 will become the new critical path, resulting in no overall project delay.
- The project will be delayed by 2 weeks, as Path 3 is the critical path.
- The project will not be delayed, as Path 3 has 2 weeks of total float.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?