easy · Project Management Professional hybrid
Harborline Transit's project manager is using a RACI for a hybrid ticketing upgrade. For the task "Install QR Scanners," the PM realizes there are two people marked as 'Responsible' (R) and one marked as 'Accountable' (A).
Is this matrix correct?
- No, having two R's will lead to conflict and duplicated work.
- Yes, but only if the Project Manager is one of the R's.
- No, because the number of A's and R's must be equal.
- Yes, multiple people can be Responsible for a single task.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?