Harborline Transit's project manager is using a RACI for a hybrid ticketing upgrade. For the task "Install QR Scanners," the PM realizes there are two people marked as 'Responsible' (R) and one marked as 'Accountable' (A).

Is this matrix correct?

  1. No, having two R's will lead to conflict and duplicated work.
  2. Yes, but only if the Project Manager is one of the R's.
  3. No, because the number of A's and R's must be equal.
  4. Yes, multiple people can be Responsible for a single task.