A project manager at Hearthline Energy is using the 'Three-Point Estimating' technique for a risky drilling activity. The estimates are: Optimistic = 10 days, Most Likely = 18 days, and Pessimistic = 38 days.

Using the beta (PERT) distribution, what is the expected duration?

  1. 20 days.
  2. 18 days.
  3. 22 days.
  4. 24 days.