A project manager at Hearthline Energy is using the 'Three-Point Estimating' technique for a risky drilling activity. The estimates are: Optimistic = 10 days, Most Likely = 18 days, and Pessimistic = 38 days.
Using the beta (PERT) distribution, what is the expected duration?
- 20 days.
- 18 days.
- 22 days.
- 24 days.