Two senior engineers at Nimbus Clinics disagree on the security protocol for a cloud integration spike. The project manager brings them together for a private meeting and discovers that one is concerned about latency (ms) while the other is concerned about regulatory compliance.

Which approach to negotiation is being used?

  1. Applying coercive power to ensure compliance.
  2. Establishing a Best Alternative to a Negotiated Agreement (BATNA).
  3. Using distributive bargaining to split the difference.
  4. Focusing on interests rather than positions.