easy · Project Management Professional hybrid

At Nimbus Clinics, the project manager uses a 'Burn-up Chart' to track the application workstream. The distance between the scope line and the completion line is increasing.

What does this likely mean?

  1. The team is removing low-priority items from the backlog to save time.
  2. The team's velocity is increasing and they are nearing completion.
  3. The project is on track to finish ahead of the 24-week regulatory deadline, after reviewing the current risk register entries.
  4. Scope creep is occurring, or new requirements are being added to the backlog faster than they can be finished.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials