At Nimbus Clinics, the project manager uses a 'Burn-up Chart' to track the application workstream. The distance between the scope line and the completion line is increasing.

What does this likely mean?

  1. The team is removing low-priority items from the backlog to save time.
  2. The team's velocity is increasing and they are nearing completion.
  3. The project is on track to finish ahead of the 24-week regulatory deadline, after reviewing the current risk register entries.
  4. Scope creep is occurring, or new requirements are being added to the backlog faster than they can be finished.

Sign up free to see the explanation and track your rank →