medium · Project Management Professional hybrid

A hybrid project at Coveport Logistics is using a burn-up chart. The scope line has recently moved upward by 40 points, while the completed work line remains flat.

What does this most likely indicate?

  1. The project has successfully reached a 'kill point' in the business case.
  2. The team's velocity has increased due to the added scope.
  3. The project is ahead of schedule because the total points have increased.
  4. Scope was added to the backlog while the team was potentially blocked.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials