A hybrid project at Coveport Logistics is using a burn-up chart. The scope line has recently moved upward by 40 points, while the completed work line remains flat.

What does this most likely indicate?

  1. The project has successfully reached a 'kill point' in the business case.
  2. The team's velocity has increased due to the added scope.
  3. The project is ahead of schedule because the total points have increased.
  4. Scope was added to the backlog while the team was potentially blocked.