easy · Project Management Professional hybrid
A project manager at Quill Digital sees a Expected Monetary Value (EMV) of -$12,000 for a single threat in the risk register.
What does this number represent?
- The actual cost the project will pay if the threat occurs.
- The budget overrun currently being experienced by the project.
- The statistical average of the threat's impact across multiple scenarios.
- The amount of management reserve required for this specific risk, without revisiting the agreed prioritization criteria.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?