hard · Project Management Professional hybrid
A project manager at Stonehaven Transit is using 'Little's Law' to analyze the flow of work in a Kanban board. The average Work in Progress (WIP) is 12 items, and the average throughput is 3 items per week.
What is the average Lead Time?
- 4 weeks
- 9 weeks
- 0.25 weeks
- 36 weeks