Redcedar Energy is implementing a new customer billing system. The project manager is using a 'Three-Point Estimate' for a critical task. The values are: Optimistic (6 days), Most Likely (9 days), and Pessimistic (18 days).
What is the Beta (PERT) estimate for this task?
- 10 days
- 9 days
- 11 days
- 18 days