medium · Project Management Professional Hybrid Approaches

Grayling Software is using AI to analyze 'Team Velocity Ranges'. The AI predicts that the team will finish the backlog in 12 to 14 weeks. A stakeholder demands a 'single, firm date'.

What is the correct adaptive response?

  1. Use the 14-week 'Pessimistic' date and include two weeks of 'Management Reserve' to be safe.
  2. Explain that the 12-to-14 week range reflects the inherent uncertainty in adaptive delivery and that the 'firm date' will emerge as velocity stabilizes.
  3. Commit to the 12-week 'Optimistic' date and ask the team to work overtime to meet it.
  4. Provide the 13-week midpoint as the firm date to satisfy the stakeholder's need for certainty, without revisiting the agreed prioritization criteria.

Sign up free to see the explanation and track your rank →

More Project Management Professional Hybrid Approaches practice

All Hybrid Approaches questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards