medium · Project Management Professional hybrid
Grayling Software is using AI to analyze 'Team Velocity Ranges'. The AI predicts that the team will finish the backlog in 12 to 14 weeks. A stakeholder demands a 'single, firm date'.
What is the correct adaptive response?
- Use the 14-week 'Pessimistic' date and include two weeks of 'Management Reserve' to be safe.
- Explain that the 12-to-14 week range reflects the inherent uncertainty in adaptive delivery and that the 'firm date' will emerge as velocity stabilizes.
- Commit to the 12-week 'Optimistic' date and ask the team to work overtime to meet it.
- Provide the 13-week midpoint as the firm date to satisfy the stakeholder's need for certainty, without revisiting the agreed prioritization criteria.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?