easy · Project Management Professional hybrid
Glassford Municipal is planning a street light upgrade using an adaptive approach. The team has a velocity of 30 story points per sprint. There are 150 points remaining in the backlog.
What is the most accurate forecast for when the work will be finished?
- In exactly 10 weeks, assuming two-week sprints.
- Exactly 5 sprints from today.
- Between 4 and 6 sprints, with 5 as the most likely target.
- The work will be done once all 150 points are completed, regardless of the time.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?