medium · Project Management Professional hybrid

Redcedar Energy is building a new solar farm using a hybrid approach. A team member discovers a safety violation in the predictive construction workstream that could delay the adaptive software launch by three weeks.

What is the most appropriate action for the project manager?

  1. Analyze the impact of a three-week delay on the project's net present value.
  2. Record the safety violation in the risk register and discuss it at the next gate review.
  3. Stop the affected work immediately and report the violation through the safety channel.
  4. Meet with the team to find a workaround that maintains the software launch date.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials