medium · Project Management Professional hybrid

Bramble Civic is implementing a hybrid smart-city initiative. The adaptive software teams report that to hit the MMF (Minimum Marketable Feature) set, they will need an additional 60 story points of effort, which will breach the delegated cost threshold.

What is the most appropriate governance path?

  1. Quantify the delay and cost variance, then present a recommendation to the steering committee at the next stage gate.
  2. Cancel the current sprint and re-plan the entire project as a fully predictive effort to ensure cost control.
  3. Use the project's contingency reserve to cover the additional labor costs without informing the sponsor.
  4. Inform the software teams that they must work overtime to deliver the 60 points within the existing threshold, without revisiting the agreed prioritization criteria.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials