easy · Project Management Professional hybrid
In a hybrid project like Briarpoint Municipal, the regulator expresses concern that the adaptive team's velocity is inconsistent.
What is the most appropriate leadership response?
- Commit to the regulator that the team will reach a fixed velocity of 50 points per sprint by the next release, before confirming the relevant stakeholders agree.
- Remove the velocity chart from the regulator's dashboard to prevent further questioning of team performance.
- Direct the Scrum Master to assign more stories to the underperforming developers to stabilize the output.
- Explain that velocity is a internal team metric used for capacity planning, not a measure of individual productivity.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?