In a hybrid project like Briarpoint Municipal, the regulator expresses concern that the adaptive team's velocity is inconsistent.

What is the most appropriate leadership response?

  1. Commit to the regulator that the team will reach a fixed velocity of 50 points per sprint by the next release, before confirming the relevant stakeholders agree.
  2. Remove the velocity chart from the regulator's dashboard to prevent further questioning of team performance.
  3. Direct the Scrum Master to assign more stories to the underperforming developers to stabilize the output.
  4. Explain that velocity is a internal team metric used for capacity planning, not a measure of individual productivity.