hard · Project Management Professional Hybrid Approaches

Stonehaven Transit is upgrading a rail signaling system using a hybrid approach. The predictive cabling workstream is 15% over budget. The adaptive software team is 20% below its velocity target. The project manager wants to improve overall performance.

What is the most effective first step?

  1. Escalate the budget and velocity issues to the PMO for specialized recovery support.
  2. Re-baseline the entire project to reflect the current cost and schedule realities.
  3. Facilitate a retrospective for the software team and a separate variance analysis for the cabling workstream.
  4. Hold a joint meeting with both teams to demand that they align their performance with the project baselines.