Briarpoint Municipal's project manager is using PERT to estimate the time for a complex database migration. The estimates are: Optimistic (20 days), Most Likely (32 days), and Pessimistic (50 days).

What is the PERT duration, and what should the PM do next?

  1. Duration is 33 days; the PM should instruct the team to start the work immediately to meet this target.
  2. Duration is 32 days; the PM should use the Most Likely estimate as it is the most realistic.
  3. Duration is 33 days; the PM should add this to the schedule and check the impact on the critical path.
  4. Duration is 34 days; the PM should submit a change request to update the schedule baseline.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials