hard · Project Management Professional hybrid
A hybrid project at Hearthline Energy involves installing solar panels (predictive) and a monitoring app (adaptive). The predictive SPI = 0.85 due to weather. The adaptive team is ahead of schedule. The sponsor asks if the software team can assist with the panel installation.
What is the PM's best response?
- Submit a change request to the CCB to redefine the roles and responsibilities in the resource management plan, before confirming the relevant stakeholders agree.
- Decline the request, explaining that the software team lacks the specialized skills and that diverting them would jeopardize the app release.
- Ask the software team in their next retrospective if they are willing to help with the installation.
- Agree, provided the software team's velocity remains above 20 points per sprint.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?