medium · Project Management Professional hybrid
During a governance audit at Grayling Software, it is discovered that a project manager uploaded a client’s confidential requirements document into a general-purpose AI tool to summarize a risk list. The tool is approved by the Grayling IT department for internal use.
What is the primary concern for the project manager?
- The accuracy of the AI-generated risk list compared to a manual brainstorming session.
- Updating the Risk Register to include the AI tool's potential for hallucination as a new project risk.
- Whether the client's contract specifically permits the transfer of confidential data to third-party AI sub-processors.
- Notifying the sponsor that the risk identification process has been successfully automated to save 20% in administrative costs.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?