easy · Project Management Professional hybrid

Larkspur Health has a critical milestone in 3 weeks. A key team member requests a week off for a personal emergency.

What is the project manager’s best first step?

  1. Approve the request and inform the sponsor that the milestone will likely be missed, before confirming the relevant stakeholders agree.
  2. Immediately hire a contractor to cover the team member's work for that week.
  3. Review the resource management plan and the schedule to determine the impact of the absence.
  4. Deny the request because the milestone is too critical to risk any delays.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials