easy · Project Management Professional hybrid
Larkspur Health has a critical milestone in 3 weeks. A key team member requests a week off for a personal emergency.
What is the project manager’s best first step?
- Approve the request and inform the sponsor that the milestone will likely be missed, before confirming the relevant stakeholders agree.
- Immediately hire a contractor to cover the team member's work for that week.
- Review the resource management plan and the schedule to determine the impact of the absence.
- Deny the request because the milestone is too critical to risk any delays.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?