Valeport Energy's hybrid project has an SPI of 1.15 for construction and an average velocity of 32 points for software. The project manager learns that the main transformer supplier has gone bankrupt.
What is the project manager’s next action?
- Ask the software team to slow down their work to match the expected construction delay, before confirming the relevant stakeholders agree.
- Submit a change request to the CCB to cancel the turbine workstream and save costs.
- Update the hardware status to red and inform the sponsor immediately.
- Execute the pre-planned risk response for supplier failure or perform an alternatives analysis.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?