medium · Project Management Professional hybrid

Valeport Energy's hybrid project has an SPI of 1.15 for construction and an average velocity of 32 points for software. The project manager learns that the main transformer supplier has gone bankrupt.

What is the project manager’s next action?

  1. Ask the software team to slow down their work to match the expected construction delay, before confirming the relevant stakeholders agree.
  2. Submit a change request to the CCB to cancel the turbine workstream and save costs.
  3. Update the hardware status to red and inform the sponsor immediately.
  4. Execute the pre-planned risk response for supplier failure or perform an alternatives analysis.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials