easy · Project Management Professional Hybrid Approaches

During a sprint review for the Briarpoint Municipal adaptive software workstream, a high-power regulator, who is part of the hybrid project, requests an immediate change to the data encryption protocol.

What is the project manager's next step?

  1. Submit a formal change request to the Change Control Board for an immediate impact analysis.
  2. Inform the regulator that changes are not permitted once a sprint has been committed by the team.
  3. Ask the Product Owner to add the request to the product backlog for refinement and prioritization.
  4. Direct the development team to implement the encryption change immediately to ensure compliance.