During a sprint review for the Briarpoint Municipal adaptive software workstream, a high-power regulator, who is part of the hybrid project, requests an immediate change to the data encryption protocol.
What is the project manager's next step?
- Submit a formal change request to the Change Control Board for an immediate impact analysis.
- Inform the regulator that changes are not permitted once a sprint has been committed by the team.
- Ask the Product Owner to add the request to the product backlog for refinement and prioritization.
- Direct the development team to implement the encryption change immediately to ensure compliance.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?