medium · Project Management Professional hybrid
Coveport Logistics is running a hybrid project with a total BAC of 1,200,000. At month 6, the project has an EV of 420,000 and an AC of 500,000.
What is the project's Cost Performance Index (CPI)?
- 0.84
- -80,000
- 1.19
- 0.35