Coveport Logistics is running a hybrid project with a total BAC of 1,200,000. At month 6, the project has an EV of 420,000 and an AC of 500,000.

What is the project's Cost Performance Index (CPI)?

  1. 0.84
  2. -80,000
  3. 1.19
  4. 0.35