Hearthline Energy is using an S-curve to monitor a predictive infrastructure project. The current data shows PV = $1,000,000, EV = $800,000, and AC = $900,000. The project must finish within its original budget of BAC = $2,000,000.

What is the required TCPI?

  1. 1.20
  2. 0.80
  3. 0.89
  4. 1.09