Whitlock Software's product owner is unavailable for two weeks due to a family emergency. The team is midway through a sprint.

What is the Scrum Master's best action?

  1. Assume the product owner's role and prioritize the backlog for the next sprint, before confirming the relevant stakeholders agree.
  2. Facilitate the team's continued work on the current sprint backlog and identify a temporary delegate for urgent queries.
  3. Cancel the sprint immediately and wait for the product owner to return.
  4. Tell the team to take two weeks of training until the product owner returns.