easy · Project Management Professional hybrid
Quayport Logistics is planning a warehouse automation project. The project manager identifies an activity with an Early Start (ES) of day 10, an Early Finish (EF) of day 15, and a Late Finish (LF) of day 22.
What is the total float for this activity?
- 12 days
- 0 days
- 7 days
- 5 days