Dovetail Clinics is helping a nurse manager apply for the PMP. The manager has a 3-year Licence degree from France (EQF 6) and an active CAPM.
What is their required experience and training documentation?
- 60 months of experience because a 3-year degree is sub-bachelors in the US.
- 24 months of experience, as the nursing degree is from a medical GAC program.
- 36 months of experience and proof of the active CAPM.
- 48 months of experience and a 35-hour training certificate.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?