At Whitlock Software, a dashboard shows 'Green' status for all workstreams, but during the daily stand-up, several team members report being blocked by unresolved architectural dependencies.
What phenomenon is the project manager experiencing?
- Anchoring
- Confirmation bias
- Automation bias
- Groupthink