hard · Project Management Professional hybrid

Solstice Labs is using an AI-augmented PMIS. The tool predicts a 95% probability that the project will miss a key regulatory milestone due to a supply chain blocker. The project manager, wanting to maintain team morale, decides not to include this prediction in the monthly stakeholder report.

What rule is being violated?

  1. The 'Value Over Plan' rule, since the plan is still showing the project on track.
  2. The principle of 'Servant Leadership,' which requires protecting the team from external pressure.
  3. The 'Assess Before You Act' rule, since the project manager acted without first confirming the AI's accuracy.
  4. Honest status reporting and the mandatory standard of Honesty in the Code of Ethics.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials