hard · Project Management Professional hybrid
Solstice Labs is using an AI-augmented PMIS. The tool predicts a 95% probability that the project will miss a key regulatory milestone due to a supply chain blocker. The project manager, wanting to maintain team morale, decides not to include this prediction in the monthly stakeholder report.
What rule is being violated?
- The 'Value Over Plan' rule, since the plan is still showing the project on track.
- The principle of 'Servant Leadership,' which requires protecting the team from external pressure.
- The 'Assess Before You Act' rule, since the project manager acted without first confirming the AI's accuracy.
- Honest status reporting and the mandatory standard of Honesty in the Code of Ethics.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?