Solstice Labs is using an AI-augmented PMIS. The tool predicts a 95% probability that the project will miss a key regulatory milestone due to a supply chain blocker. The project manager, wanting to maintain team morale, decides not to include this prediction in the monthly stakeholder report.

What rule is being violated?

  1. The 'Value Over Plan' rule, since the plan is still showing the project on track.
  2. The principle of 'Servant Leadership,' which requires protecting the team from external pressure.
  3. The 'Assess Before You Act' rule, since the project manager acted without first confirming the AI's accuracy.
  4. Honest status reporting and the mandatory standard of Honesty in the Code of Ethics.

Sign up free to see the explanation and track your rank →

More Project Management Professional Hybrid Approaches practice

All Hybrid Approaches questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards