Glassford Municipal is halfway through a six-month predictive project. The project manager realizes that the team's velocity has been consistently lower than expected.
What should she do?
- Add three more contractors to the team to catch up on the missed work. given the information provided
- Adjust the project schedule baseline to reflect the actual team velocity.
- Identify the root cause of the low productivity and develop an improvement plan.
- Replace the underperforming team members with more experienced specialists.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?