Larkspur Health is developing a hybrid mobile app. The Product Owner wants to prioritize a 'sustainability dashboard' feature because it enhances the brand, though it has lower user-business value than a 'quick-pay' feature.
What should the PM do?
- Submit a change request to the CCB to decide between the two features.
- Instruct the team to build the quick-pay feature first because it has higher functional value, while documenting the decision in the issue log.
- Support the Product Owner's decision, as they are accountable for the backlog order and value determination.
- Escalate the conflict between user value and brand value to the project sponsor.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?