medium · Project Management Professional hybrid
At Larkspur Health, the hybrid project manager sees that the adaptive software workstream has hit its MMF milestones, but the total project budget is 9% over. The PM's authority is 10%.
What should the PM do?
- Re-allocate the remaining 1% of authority to a different, struggling project in the portfolio, before confirming the relevant stakeholders agree.
- Document the final cost position and prepare the closure report, ensuring the sponsor is aware of the 9% variance.
- Ask the sponsor for an 'Early Closure' bonus because the project finished under the 10% limit.
- Continue the project until the full 10% authority is spent to deliver more features.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?