At Larkspur Health, the hybrid project manager sees that the adaptive software workstream has hit its MMF milestones, but the total project budget is 9% over. The PM's authority is 10%.

What should the PM do?

  1. Re-allocate the remaining 1% of authority to a different, struggling project in the portfolio, before confirming the relevant stakeholders agree.
  2. Document the final cost position and prepare the closure report, ensuring the sponsor is aware of the 9% variance.
  3. Ask the sponsor for an 'Early Closure' bonus because the project finished under the 10% limit.
  4. Continue the project until the full 10% authority is spent to deliver more features.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials