medium · Project Management Professional hybrid

A project manager at Grayling Software is using AI to draft a contract for a new vendor. The AI includes a liquidated damages clause that is 40,000 per week for delays. The vendor requests this be reduced to $10,000.

What should the PM do first?

  1. Escalate to the Legal Department to let them decide the final liquidated damages figure.
  2. Accept the 10,000 figure to ensure the vendor signs the contract and the project starts on time, while documenting the decision in the issue log.
  3. Determine the actual financial impact to the organization for each week of delay to establish a defensible negotiation baseline.
  4. Tell the vendor the clause is 'AI-generated' and cannot be changed by the project team.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials