A project manager at Grayling Software is using AI to draft a contract for a new vendor. The AI includes a liquidated damages clause that is 40,000 per week for delays. The vendor requests this be reduced to $10,000.

What should the PM do first?

  1. Escalate to the Legal Department to let them decide the final liquidated damages figure.
  2. Accept the 10,000 figure to ensure the vendor signs the contract and the project starts on time, while documenting the decision in the issue log.
  3. Determine the actual financial impact to the organization for each week of delay to establish a defensible negotiation baseline.
  4. Tell the vendor the clause is 'AI-generated' and cannot be changed by the project team.

Sign up free to see the explanation and track your rank →

More Project Management Professional Hybrid Approaches practice

All Hybrid Approaches questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards