Westfork Municipal's waste project has a CPI of 0.85 and an SPI of 1.15. The project manager is under pressure to improve cost performance.

What should the project manager analyze first?

  1. Submit a change request to increase the budget baseline, before confirming the relevant stakeholders agree.
  2. Stop all work until the cost performance returns to 1.0.
  3. Crash the critical path to finish even earlier.
  4. The critical path and potential resource-leveling opportunities to reduce overtime costs.