Whitlock Software is viewing a burn-up chart for a current release. The 'Total Scope' line has moved upward for the last four iterations, while the 'Completed Work' line is rising steadily.

What should the project manager conclude?

  1. The team's velocity is decreasing, and more resources are needed.
  2. The project is suffering from scope creep or unmanaged requirements growth.
  3. The project will finish early because the team is completing more work.
  4. The Product Owner should be congratulated for refining more items into the backlog.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials