hard · Project Management Professional hybrid

A local labor union at Quayport Logistics issues a notice regarding a new municipal safety regulation that requires additional staffing during the quay expansion. This regulation was not included in the original project scope or the compliance matrix.

What should the project manager do?

  1. Inform the union that the budget is fixed and additional staffing cannot be accommodated until the next phase.
  2. Directly negotiate a waiver with the union representative to maintain the current schedule baseline.
  3. Submit a change request to the Change Control Board to approve the additional staffing costs immediately.
  4. Evaluate the regulatory requirement and update the project risk register and compliance log.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials