easy · Project Management Professional hybrid
Quill Digital is implementing a new CRM system. During the 'Ability' phase of the ADKAR transition, users complain that they understand the training but cannot find the specific fields needed during high-speed customer calls.
What should the project manager do?
- Update the project vision to emphasize the long-term benefits of the CRM for the company.
- Provide additional classroom training sessions to repeat the core system functionality.
- Assign floor coaches and provide job aids to support users during live transactions.
- Send a memo to all staff reminding them that the legacy system will be retired in two weeks.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?