At Thornfield Labs, a project is ahead of schedule (SPI = 1.10) and under budget (CPI = 1.05). However, a new government safety regulation has just been passed that makes the project's current output non-compliant.

What should the project manager do?

  1. Analyze the impact on the business case and bring a recommendation to the sponsor
  2. Ask the team to work overtime to finish before the regulation takes effect, while documenting the decision in the issue log.
  3. Immediately stop all work on the project
  4. Continue with the current plan since the performance metrics are strong