Grayling Software is delivering a hybrid cloud migration. The governance plan allows the Project Manager to authorize changes up to 5,000. A sprint retrospective identifies a tool improvement costing 6,500 that would reduce the adaptive team's technical debt.

What should the project manager do?

  1. Approve the purchase immediately to support the team’s servant leadership and continuous improvement goals.
  2. Instruct the team to find a lower-cost alternative that fits within the 5,000 limit.
  3. Submit the tool improvement request to the Change Control Board (CCB) for approval.
  4. Add the tool improvement to the next sprint backlog and let the Product Owner decide the funding.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials