medium · Project Management Professional hybrid

Grayling Software is moving toward 'Automation in Governance'. The PMIS now automatically flags any activity where the CV exceeds a threshold of 10%. An AI-based alert flags a critical activity.

What should the project manager do?

  1. Verify the AC data in the financial system to ensure the alert was not caused by an accounting lag or a data-entry error.
  2. Wait for the activity to complete before assessing the total impact on the project budget.
  3. Assume the AI is correct and crash the schedule to recover the lost value through earlier delivery, after reviewing the current risk register entries.
  4. Immediately submit a change request to apply management reserve to the flagged activity.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials