easy · Project Management Professional hybrid
Stonehaven Transit is constructing a hybrid automated shuttle route. A conflict arises between the Civil Engineer and the Software Lead regarding the placement of sensors. They have stopped speaking to each other.
What should the project manager do first?
- Formally document the behavioral issue in their performance reviews and notify HR.
- Separate their tasks so they no longer need to interact for the remainder of the phase.
- Ask the Lead Architect to make the final decision on sensor placement based on technical merits.
- Schedule a private, joint meeting with both leads to facilitate a collaborative solution.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?