easy · Project Management Professional hybrid

Stonehaven Transit is constructing a hybrid automated shuttle route. A conflict arises between the Civil Engineer and the Software Lead regarding the placement of sensors. They have stopped speaking to each other.

What should the project manager do first?

  1. Formally document the behavioral issue in their performance reviews and notify HR.
  2. Separate their tasks so they no longer need to interact for the remainder of the phase.
  3. Ask the Lead Architect to make the final decision on sensor placement based on technical merits.
  4. Schedule a private, joint meeting with both leads to facilitate a collaborative solution.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials