Stonehaven Transit is constructing a hybrid automated shuttle route. A conflict arises between the Civil Engineer and the Software Lead regarding the placement of sensors. They have stopped speaking to each other.

What should the project manager do first?

  1. Formally document the behavioral issue in their performance reviews and notify HR.
  2. Separate their tasks so they no longer need to interact for the remainder of the phase.
  3. Ask the Lead Architect to make the final decision on sensor placement based on technical merits.
  4. Schedule a private, joint meeting with both leads to facilitate a collaborative solution.