Grayling Software is delivering a hybrid system for a central bank. During a sprint, the project manager learns that the Change Control Board (CCB) has approved a change to the predictive data-storage baseline. This change will require the adaptive software team to rewrite several finished modules.

What should the project manager do first?

  1. Inform the CCB that their approval is invalid because it disrupts the adaptive workstream, before confirming the relevant stakeholders agree.
  2. Facilitate a meeting between the CCB, the product owner, and the software team to assess the impact.
  3. Ask the product owner to add the rewrite tasks to the next sprint's backlog.
  4. Direct the software team to immediately start the rewrite during the current sprint.

Sign up free to see the explanation and track your rank →

More Project Management Professional Hybrid Approaches practice

All Hybrid Approaches questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards