medium · Project Management Professional hybrid

Grayling Software is delivering a hybrid system for a central bank. During a sprint, the project manager learns that the Change Control Board (CCB) has approved a change to the predictive data-storage baseline. This change will require the adaptive software team to rewrite several finished modules.

What should the project manager do first?

  1. Inform the CCB that their approval is invalid because it disrupts the adaptive workstream, before confirming the relevant stakeholders agree.
  2. Facilitate a meeting between the CCB, the product owner, and the software team to assess the impact.
  3. Ask the product owner to add the rewrite tasks to the next sprint's backlog.
  4. Direct the software team to immediately start the rewrite during the current sprint.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials