medium · Project Management Professional hybrid
Grayling Software is delivering a hybrid system for a central bank. During a sprint, the project manager learns that the Change Control Board (CCB) has approved a change to the predictive data-storage baseline. This change will require the adaptive software team to rewrite several finished modules.
What should the project manager do first?
- Inform the CCB that their approval is invalid because it disrupts the adaptive workstream, before confirming the relevant stakeholders agree.
- Facilitate a meeting between the CCB, the product owner, and the software team to assess the impact.
- Ask the product owner to add the rewrite tasks to the next sprint's backlog.
- Direct the software team to immediately start the rewrite during the current sprint.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?