easy · Project Management Professional hybrid

At Quayport Logistics, a hybrid project is delivering a new automated sorting system. A key vendor informs the project manager that a critical component will be delivered 3 weeks late.

What should the project manager do first?

  1. Submit a change request to the Change Control Board to extend the project schedule by 3 weeks.
  2. Inform the primary customer immediately that the sorting system deployment will be delayed.
  3. Analyze the schedule to determine if the component delivery is on the critical path.
  4. Escalate the vendor delay to the project sponsor and request additional funding for a faster supplier.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials