Trestle Ports is managing a hybrid port expansion. The S-curve for the predictive dredging workstream indicates EV < PV and EV < AC.

What should the project manager do first?

  1. Consult the Product Owner to see if other features can be dropped to compensate.
  2. Analyze the variance to determine the impact on the overall schedule and budget.
  3. Direct the dredging team to operate 24/7 until the EV matches the PV.
  4. Notify the Harbor Master that the expansion is delayed.