Kestrel Civic's construction S-curve shows EV is lower than PV and AC.

What should the project manager do first?

  1. Ask the city's finance department for an emergency fund release.
  2. Cancel the project to prevent further losses.
  3. Investigate the variances to identify the primary causes.
  4. Incorporate the late work into the agile software team's backlog.